Here we are with our Week Three update!

Underground plumbing has been completed, the inspection passed on Friday 1st, and this afternoon (Monday), the concrete patching was completed.

Starting tomorrow, the walls start going up, so when we post next weeks update, you will really see some big changes!

Don't forget to sign up for our mailing list (we promise, no spam), and if you have a question or comment drop us an email at info@OswegoBrewing.com or contact us via FaceBook.

See you back here next week!